Track how AI data center buildouts are reshaping power grids, labor markets, and AI product roadmaps in 2025.
| Metric | Why It Matters | Example 2024 Data Points |
|---|
| Build cost per MW | Indicates capital efficiency; impacts pricing of AI services | Turner & Townsend’s 2024 index places U.S. builds at **$8–12 million per MW** in primary markets |
| Power Usage Effectiveness (PUE) | Proxy for energy efficiency and operating cost | New hyperscale facilities target **PUE ≤ 1.2**; older enterprise sites average ~1.4 |
| Renewable match (%) | Shows alignment with sustainability commitments | Google reported a **64% hourly renewable match in 2023** and aims for 24/7 clean energy by 2030 |
| Job-years per billion dollars | Helps quantify community impact | U.S. Council of Economic Advisers uses **~8,500 construction jobs per $1 billion invested** in digital infrastructure |
| Lead time for high-voltage interconnect | Determines project critical path | PJM and ERCOT interconnection queues now run **24–36 months** for large loads |