Planning Implications for Product and Infra Teams
Treat power and land as product dependencies. If your AI roadmap relies on GPU clusters, partner early with facilities and energy teams to secure megawatts and ensure renewable procurement aligns with corporate climate targets.
Model total cost of ownership (TCO) with grid upgrade timelines. Power transformers and switchgear lead times can exceed 18 months. Delays ripple into deployment schedules and capitalized software costs.
Build multi-region redundancy into training plans. Regulatory approvals (e.g., in Dublin or Singapore) may cap capacity. Distribute workloads across jurisdictions to hedge policy or grid risks.
Track subsidies and tax credits. The U.S. CHIPS and Science Act and EU Important Projects of Common European Interest (IPCEI) programs both include grants that reduce effective build costs when AI projects meet domestic manufacturing or sustainability criteria.